While most field resources for a particular company should see the countdown that displays the estimated

By | December 7, 2022

While most field resources for a particular company should see the countdown that displays the estimated time remaining for an activity in Oracle Field Service Cloud (OFSC), their ‘contractor resources’ that only perform periodica work should NOT see it.
Which configuration supports the requirement to hide the countdown timer for those ‘contractor resources’ that do NOT need to see it when they are working on their assigned activities?

Correct Answer: B